By Kaitlyn Clark
The Haldimand Press
DUNNVILLE—Mapleview Elementary School is about $1.1 million overbudget and is awaiting final confirmation of all soil costs before asking the Ministry for additional funds, but the best-case scenario still leaves Grand Erie District School Board (GEDSB) paying $421,000 out of reserves. This brings the final project cost to $12.5 million.