Council, staff taking steps to deliver county-wide broadband internet service

Featured image for Council, staff taking steps to deliver county-wide broadband internet service

To The Haldimand Press

HALDIMAND—Haldimand County Council is moving forward with its commitment to bringing affordable, reliable high-speed internet service to all residents. On July 16, 2019, staff released a Request for Pre-Qualification (RFPQ) to short-list internet service providers capable of installing broadband infrastructure and facilitating county-wide internet services.

The RFPQ is an invitation by Haldimand County to prospective bidders to submit proposals outlining their qualifications and experience. In order to make the RFPQ short list, bidders must demonstrate their ability – across multiple evaluation criteria – to facilitate county-wide internet services in the long term.

Bidders who meet the requirements outlined in the RFPQ and receive a passing score will be allowed to progress to the final selection stage.

It is anticipated that at the conclusion of the RFPQ process, staff will report back to Council and seek direction to initiate a Negotiated Request for Proposal process (NRFP) with a shortlisted number of proponents. Ultimately, negotiations will result in the selection of a successful bidder to install and facilitate internet services throughout all of Haldimand’s communities.

“This is an important step in making affordable, reliable high-speed internet available to all residents,” said Haldimand County Mayor Ken Hewitt. “A reliable internet connection is not a luxury – it’s a necessity. Everyone in Haldimand County deserves access to this vital and basic service, whether it’s to stay connected with family, take care of day-to-day tasks, complete an online course, or sustain a business.”

Community consultations will take place as the project progresses to obtain resident input, assess needs, and address questions or concerns related to broadband internet service.

“We are committed to finding a financially sound, practical solution that makes internet connectivity attainable and sustainable for all. We’ll keep the public informed and engaged as the project moves forward,” added Mayor Hewitt.

 

Approximate project timeline – as listed in the RFPQ

Issue RFP – July 16, 2019 to August 16, 2019

Evaluate RFPQ proponents – August 19, 2019 to August 22, 2019

Issue NRFP to qualified bidders – September 24, 2019 to October 29, 2019

Evaluate NRFP – October 30, 2019 to November 4, 2019

Negotiations with proponents – November 5, 2019 to November 26, 2019

Report to Council for approval of recommended bidder – December 16, 2019

Construction – Spring 2020 to January 2025*

*Timelines are established based on a tentative contract execution date of January 2020 and are subject to change.